PT. Supra Surya Indonesia

 

 

PT. ROBERTS SCHAEFER SOROS INDONESIA (USD 313,214.00)

  • Supply Material For Job 1007 (USD 97,294.00)
  • Counter Weight Detail (USD 28,240.00)
  • Truck Pad Steel (USD 31,510.00)
  • Surge Bin Reinforcement (USD 4,700.00)
  • Fabrication for Panel 6 & 7 (USD 151,470.00)

 

 

WILMAR GROUP (IDR 14,375,228,000.00)

  • Pipe Rack Refinery Tank (IDR 337,136,000.00)
  • NPK 3 (IDR 14,038,092,000.00)

 

 

PT. BATUTUA TEMBAGA RAYA (IDR 5,050,828,000.00)

  • Wetar Project - UDP Restart (IDR 1,365,000,000.00)
  • Wetar Preliminary Steel & Copper Busbar (IDR 204,403,000.00)
  • Wetar - 850 KL Tank (IDR 2,362,920,000.00)
  • Wetar Mechanical MTO (IDR 503,470,000.00)
  • Hydraulic Manual Valve (IDR 12,230,000.00)
  • Installation Cost 850 KL Tank (IDR 602,805,000.00)

 

PT. PETROSEA (IDR 4,335,445,400.00)

  • ABN Workshop Extension Facilities

 

PT. DWINAD NUSA SEJAHTERA (IDR 2,306,440,699.00)

  • Tembang Gold Project – Structural & Mechanical Works (IDR 12,328,173,750.00)
  • Concrete Works (IDR 2,028,831,000.00)
  • Tembang Gold Project – Package II (IDR 10,311,488,000.00)
  • Tembang Gold Project – Elution & Acid Wash Column (IDR 1,405,239,000.00)
  • Tembang Gold Project – Package III
  • Repair Lime Mixing Tank (IDR 25,215,400.00)

 

PT. SORINI (IDR 1,816,785,000.00)

  • Fructose Project Sorini
  • Circulation Tank
  • Additional Civil Fructose
  • Maldex Food Safety Project
  • Bug Project

.